Java 8 is not supported for versions from the intra-mart e Builder for Accel Platform 2014 Winter to 2015 Summer. What should I do?

 
[Answer]
Added Java8 on the operation environment from the intra-mart Accel Platform 2014 Winter and 2015 Spring.
The intra-mart e Builder for Accel Platform 2014 Winter and 2015 Spring corresponding above uses eclipse3.7.2 as a base.
Confirmable functions to Java8 cannot be used on eclipse3.7.2.
Therefore, operation validation for Java7 is executed on versions from the intra-mart e Builder for Accel Platform 2014 Winter to 2015 Summer.

Please follow the instructions below when developing an application to operate on the intra-mart Accel Plarform with Java8 by using above e Builder.

1. Start e Builder: Start with Java7
2. Compiler confirmable level of e Builder: Specify Java7
3. Create an user module (imm file) (Create based on Java7)
4. Debug server: Operate with Java8

Applications created with Java7 by using e Builder operates on iAP of Java8 because Java8 is compatible to Java7.

[Added on December 1, 2015]
intra-mart e Builder for Accel Platform 2015 Winter released on December 1, 2015, now can be started using Java8.
Customers using intra-mart e Builder for Accel Platform 2015 Summer or earlier versions need to install and set again to use 2015 Winter.

-- Target -----------------------------------------------------------------------------
iAP/Accel Extensions/intra-mart e Builder for Accel Platform 2014 Winter
iAP/Accel Extensions/intra-mart e Builder for Accel Platform 2015 Spring
iAP/Accel Extensions/intra-mart e Builder for Accel Platform 2015 Summer
------------------------------------------------------------------------------------------


FAQID:540
Was this article helpful?
0 out of 0 found this helpful
Powered by Zendesk